Ditch Inspection Request
Please Note:
- PUD crews will install the customer provided sweep into an existing padmount transformer or handhole. DO NOT PLUMB SWEEP INTO TRANSFORMER OR HAND HOLE (the trench must be accessible).
- The trench for conduit shall be to the edge of a padmount transformer or handhole.
- Communications conduit shall be swept up 1-ft to the right/backside of the padmount transformer or handhole when facing the front (labeled side), unless otherwise approved.
- For single phase 600 and 800 amp services, install two (2) 3” gray schedule 40 conduits.
- Conduit must be inspected by PUD personnel prior to backfilling.
- When backfilling, install Douglas County PUD supplied warning tape 12”- 18” above power conduit.
- Conduit must be backfilled to final grade prior to PUD crews installing wire.